On the 20th, the Vice Chairman of the Lishui Municipal Political Consultative Conference visited for inspection and guidance, accompanied by Vice Chairman Lu of the County Political Consultative Conference.
Power was delivered on the 11th, and the first # 450 rolling mill was successfully debugged on May 15th; On the 12th, the third workshop was completed and accepted.
On the 6th, Secretary Mo Liang conducted research, on the 9th, under the guidance of Chairman Liao, on the 21st, County Mayor Liang inspected, on the 28th, the development zone was listed, and leaders at all levels inspected. On the 29th, Workshop 1 and Workshop 2 were completed.
The company's party branch was established, emergency drills and perforation furnace debugging were successful, leadership guidance was provided, and the fourth workshop was completed.
On the 2nd, under the guidance of Chairman Chen of the Yuyao Municipal Political Consultative Conference, on the 4th, the sewage treatment center conducted a trial run, and on the 19th, the finished product furnace was ignited.
On the 6th, leaders of the Lishui Municipal Political Consultative Conference visited the company for inspection and research
On the 29th, leaders at all levels of the Songyang County Committee came to our company for inspection and research.
On the 6th, the planning land permit was obtained. On the 7th, the property rights of the factory were transferred. On the 11th, the wastewater treatment contractor was appointed. On the 12th, the construction design drawings were submitted. On the 13th, the planning permit was obtained and the water supply contract was signed. On the 15th, the construction drawings were reviewed. On the 20th, the construction supervisor was selected and signed. The wastewater treatment design was approved. On the 21st, the 81.8 million project contract was signed. On the 22nd, the red line was set out. On the 23rd, the supervision unit was appointed. On the 25th, the construction permit was obtained. On the 26th, the city leaders inspected the.
On the 1st, the park project promotion meeting was attended by County Mayor Lu. On the 21st, the groundbreaking ceremony was attended by county leaders. On the 26th, excavation for workshops 2 and 4 started.
On the 9th, the Gu Shi Land Office of the Land and Resources Bureau processed a temporary land certificate.
On the 7th, the foundation pit of the fourth workshop pier was inspected and cement was poured.
On the afternoon of the 13th, Mayor Wu Xiaodong of Lishui City and other city and county leaders inspected the Chishou construction site.
Complete project feasibility report and evaluation approval; Establishment and filing of construction projects with the National Development and Reform Commission; Design and complete the factory renderings, comprehensive building and workshop architectural drawings.
Equipment layout and company planning diagram completed; Sign the admission agreement on the 12th; Received environmental impact assessment approval on the 21st; On the 23rd, the application and certification of pollutant discharge rights will be processed, and the land will be delisted; The workshop construction drawings will be completed on the 28th; The geological exploration report will be completed on the 30th, and the rolling mill equipment contract will be signed.